Home Business AfDB-backed MNWAP Phase II advances with Ethemba Dam assessment
Business

AfDB-backed MNWAP Phase II advances with Ethemba Dam assessment

Share
MNWAP is being implemented in phases, with the first phase comprising the Mpakeni Dam and downstream conveyance and irrigation infrastructure. According to the September 2026 report, construction of Mpakeni Dam under Phase I, Component 1A, is underway.(File pics)
Share

MBABANE – The African Development Bank-backed Mkhondvo-Ngwavuma Water Augmentation Programme Phase II has advanced through updated environmental and social assessments.

This marks progress towards a major water infrastructure investment intended to expand irrigation, strengthen food security and improve energy supply in Eswatini. The progress is reflected in a September 2026 Environmental and Social Impact Assessment (ESIA) and Environmental and Social Management Plan (ESMP) report prepared for the Eswatini Water and Agricultural Development Enterprise (EWADE), the government agency responsible for implementing the project.

The report focuses on the proposed Ethemba Dam and water-transfer tunnel, which form the second phase of the Mkhondvo-Ngwavuma Water Augmentation Programme (MNWAP). However, the updated assessment remains part of the project preparation process, with the report indicating that it must be submitted to the African Development Bank (AfDB) for clearance before being reviewed by the Eswatini Environment Authority (EEA) for approval.

The environmental authorisation is a requirement before implementation can proceed.

E949.9 million for resettlements

MBABANE – The indicative resettlement budget is estimated at approximately E949.9 million, equivalent to about US$58.7 million in the report.

The document makes clear that this is a planning estimate based on the assets identified and the proposed resettlement process. It should, therefore, not be interpreted as a final amount already approved or paid to affected households.

The resettlement planning covers various assets, including residential buildings, fruit trees, schools, a clinic and other community facilities that may be affected by the dam and associated infrastructure.

The report also records concerns raised during consultations, including questions about the relocation areas, the treatment of affected assets and the timing of resettlement.

These issues underline the importance of completing the required consultation, compensation and relocation processes before activities that would cause displacement are undertaken.

The proposed management framework includes a grievance redress mechanism through which affected people can raise complaints and seek resolution of disputes associated with the project.

A total of 651 households, with a population of 3 500 have been identified within the directly affected area. Approximately 72 per cent below the age of 35, including a substantial proportion of children and youth, indicating high dependency ratios and future pressure on employment and services.  Household composition is predominantly male-headed (73 per cent), with female-headed households accounting for 27 per cent. With regard to loss of community infrastructure, 52 community assets, which include schools, churches, dipping tanks and 39 shops and small enterprises will inundated.

These consist of two schools with 701 learners, 30 teachers and eight support staff – located at Mkhitsini, one clinic at Mkhitsini, 39 businesses and enterprises at Mgomfelweni.

It also includes three sporting/recreational facilities at Mkhitsini, one dip tank servicing 60 homesteads at Mkhitsini. The community assets are utilised by an estimated population of 5 500 people.

Ethemba Dam to store 540 million cubic metres

MBABANE – MNWAP Phase II will involve the construction of Ethemba Dam on the Mkhondvo River, alongside a 27.9-kilometre water-transfer tunnel connecting the reservoir to the Ngwavuma River.

The dam is designed to store approximately 540 million cubic metres of water, which would be transferred through the tunnel to augment supplies into the Mpakeni Dam, the principal water-storage component under the programme’s first phase.

The proposed dam will be a roller-compacted concrete gravity structure with a maximum height of 121.5 metres from its foundation.

The tunnel, with an excavation diameter of 3.8 metres, is expected to transport water from the reservoir towards a planned hydropower facility on the Ngwavuma River.

The project also includes a 5-megawatt hydropower plant, which would generate renewable electricity before discharging water into the river system for downstream use.

These infrastructure components are intended to strengthen the country’s capacity to store and distribute water, particularly for agricultural production in the southern Lowveld.

Share
Written by
Nhlanganiso Mkhonta

Nhlanganiso Mkhonta serves as Business Editor at the Times of Eswatini. He reports on business, economics, finance, investment, entrepreneurship and public policy, producing insightful coverage and analysis of the issues driving Eswatini’s economy and the wider African business environment.

Don't Miss

MaMkhize’s Bull faces police test

MBABANE – Shauwn ‘MaMkhize’ Mkhize’s Mbabane Highlanders AM face their sternest MTN Premier League test yet when they meet Royal Leopard at Mayaluka...

Hyundai Creta arrives with bold new attitude

Hyundai Eswatini has wel­comed the all-new Hyundai Creta to the local market, bringing a sharper look, upgraded technology and a choice of confident...

FNB demands over E14 million from two ex-employees

MBABANE – First National Bank (FNB) has instituted High Court proceedings against two of its former employees, seeking more than E14 million in...

Ezulwini Palazzo partnership targets world-class status

MBABANE – A landmark hotel management partnership is set to position Ezulwini Palazzo as a world-class destination connecting Eswatini with SADC, Africa and...

Swallows appeal to fans for financial help

MBABANE – MTN Premier League giants Mbabane Swallows have appealed to fans for donations of at least E50 as financial pressures threaten the...

Related Articles

Africa urged to turn seed summit into jobs

MBABANE - Africa has been urged to turn commitments made at the...

ESWACAA eyes E12bn investment, 20 000 jobs by 2037

MBABANE - Eswatini Civil Aviation Authority (ESWACAA) is targeting to attract E12...

Swati-owned Datamatics lands key role in E12bn airport strategy

MBABANE - Information technology and Geographic Information Systems (GIS) consultancy Datamatics Eswatini...

UNDP backs UniPod to build production for airport cargo

MBABANE - The United Nations Development Programme (UNDP) is supporting the development...