Home Business LUSIP-II delivers all set targets – AfDB
Business

LUSIP-II delivers all set targets – AfDB

Share
It was established that the sugarcane industry is quite well established and directly supports LUSIP-II farmers to ensure continued production and supply of quality sugarcanes after Project closure.(Pics: EWADE)
Share

MBABANE – The Lower Usuthu Smallholder Irrigation Project Phase II (LUSIP-II) has delivered its targeted agricultural production outcomes.

The African Development Bank (AfDB) Project Completion Report says the project made significant progress in transforming subsistence farmers into commercial agricultural producers, although delays in developing on-farm infrastructure affected the full realisation of its development objectives.

LUSIP-II, implemented in Eswatini with a total African Development Bank financing commitment of about E855.1 million, was designed to increase agricultural production and household incomes while reducing poverty in the project area.

The project built on the first phase of the Lower Usuthu Smallholder Irrigation Project and focused on expanding access to irrigation water, strengthening agricultural production and establishing market linkages for smallholder farmers.

According to the completion report, the project ultimately achieved its targeted crop-output indicators.

Sugar cane production reached 440 000 metric tonnes against the same target, representing 100 per cent achievement.

Banana production also reached its target of 14 790 metric tonnes, while maize production reached 5 792 metric tonnes and sugar beans 1 622 metric tonnes.

The report rated the project’s development objective as highly satisfactory, although its overall project completion rating was satisfactory.

A major part of LUSIP-II involved constructing the water infrastructure required to support commercial agriculture.

The Main Conveyance System (MCS) included the remodelling of infrastructure from LUSIP-I, a new main supply system, bulk water storage reservoirs and a Supervisory Control and Data Acquisition (SCADA) system.

The project completed 5 988 metres of siphon infrastructure and 33 262 metres of lined main canal, while all five planned bulk reservoirs were completed.

The SCADA system was also established, while four potable water supply schemes were completed and commissioned.

The AfDB report says the completed main conveyance infrastructure became fully operational and supported irrigation covering more than 5 200 hectares.

This infrastructure created the foundation for supplying water to smallholder farmers and enabled the project to pursue its broader objective of moving rural households towards commercial farming.

The secondary irrigation distribution system was also completed and made operational.

However, the report notes that the pace of development was not uniform across the project.

While the main conveyance and secondary distribution systems progressed well, on-farm infrastructure development lagged behind.

This included infrastructure directly connected to agricultural production, such as roads, drainage systems, irrigation equipment and land preparation.

The delays affected the ability of some farmer companies to begin production as originally planned.

Project delayed by two years

MBABANE – Despite the infrastructure and production gains, LUSIP-II took considerably longer to implement than originally planned.

The project was initially expected to take 4.7 years, but actual implementation took 7.5 years.

The completion report attributes the delays to several factors, including the COVID-19 pandemic, which caused an almost two-year disruption.

National unrest during 2020 and 2021 also contributed to implementation delays, while land acquisition and stakeholder engagement took longer than anticipated.

Delays in the release of funds also affected implementation.

In 2024, government had allocated E102.145 million for the project but released E80.023 million.

The report says this shortfall affected progress on some components, particularly farm development and the commencement of planting by targeted farmer companies.

The timeliness component of project efficiency was consequently rated at two, despite other areas receiving stronger assessments.

Share
Written by
Nhlanganiso Mkhonta

Nhlanganiso Mkhonta serves as Business Editor at the Times of Eswatini. He reports on business, economics, finance, investment, entrepreneurship and public policy, producing insightful coverage and analysis of the issues driving Eswatini’s economy and the wider African business environment.

Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Don't Miss

Socialites, banker arrested in E396 000 fraud case

MANZINI – Two socialites and a banker have been arrested in connection with an alleged fraud involving more than E396 000. The accused...

34 cops graduate in police science

MANZINI – Thirty-four police officers have graduated with diplomas in Police Science as the police service seeks to strengthen its response to emerging...

Indlovukazi arrives in UAE for official visit

Her Majesty Indlovukazi has arrived safely in the United Arab Emirates (UAE) where she is on an official visit. Her Majesty arrived around...

MaMkhize back for ‘Bull’ after China trip

MBABANE – Mbabane Highlanders AM president Shauwn ‘MaMkhize’ Mkhize is back home after a business trip to China, declaring that her presence is...

Prince Africa Zulu appointed royal vice chancellor

MBABANE – King Misuzulu kaZwelithini has appointed Prince Africa Zulu of Onkweni as Royal Vice Chancellor of the Zulu Kingdom. The appointment took...

Related Articles

FNB launches enhanced eWallet Plus service

MBABANE - FNB Eswatini has launched eWallet Plus, an enhanced version of...

AfDB backs reforms as arrears fall to E2.7bn in 3yrs

MBABANE - Government arrears have declined to E2.7 billion as Eswatini advances...

Select’s parent SBC posts mixed interim results

MBABANE – Select’s parent company, SBC Limited reported mixed financial results, with...

US Embassy to auction vehicles, furniture, electronics

MBABANE - The US Embassy in Eswatini will auction a range of...