E2.5bn road awaits contractor two months after deadline

Share
The Ministry of Public Works and Transport says the cost for rehabilitation of roads is unavoidable because of the consistent rain and high volume of vehicles travelling on roads as evidenced by this pothole at Siphocosini (Pics: Mfanukhona Nkambule)
Share

MBABANE – The contractor for the MR14 and MR15 roads has still not been announced, despite earlier indications that this would be done by the end of October 2025.

However, on November 7, 2025, a document was prepared indicating that the date of contract award would be December 15, 2025. In bidding terminology, the date of contract award refers to the official day on which a project owner (usually a government ministry or agency) formally grants a contract to a successful bidder or contractor.

Sources explained that this marks the point when the tendering or procurement process ends and the implementation phase begins. On this date, the winning contractor is usually notified in writing that they have been selected to carry out the project. It may also be the date from which the timelines, obligations and performance periods stated in the contract begin to apply.

In short, it is the date when the project officially moves from planning to execution.

MR14 and MR21 relate to the 105.9 km section of the Siphofaneni–Sithobelath–Maloma–Nsoko (MR14) and Maloma–Siphambanweni (MR21) roads. This is a project of the Government of the Kingdom of Eswatini, financed by the African Development Bank (AfDB).

Motivating the rationale for the road’s construction, government stated that these upgrades would reduce travel times and vehicle operating costs while boosting connectivity between agriculturally rich areas and other regions.

Moono Mupotola, the AfDB Country Manager for Eswatini, was quoted months ago as saying that the project would contribute to poverty reduction by creating jobs for the youth, adding that ‘this will be achieved through targeted vocational training and apprenticeship programmes’. This was reinforced by the Minister for Public Works and Transport, Chief Ndlaluhlaza Ndwandwe. Up to 200 jobs are expected to be created.

In an interview on Friday, Sandziso Malinga, the Communications Officer for the Ministry of Public Works and Transport, said the issue was still under process, following the necessary procedures and working within the ministry’s timelines to ensure satisfaction with the dictates of the evaluation report.

After that, Malinga said, government would be in a position to announce the company to be contracted to build the road. The date of contract award pertains to the civil works and the Environmental and Social Management Plan (ESMP) for the upgrading of MR14 and MR21.

The ESMP primarily refers to an Environmental and Social Management Plan.

It has been learnt that civil works in a road project refer to the physical construction activities and infrastructure development carried out on the ground during the project.

Research has shown that these include:

Site preparation – clearing vegetation, demolishing existing structures and levelling the ground.

Earthworks – excavation, filling, grading and compaction of the soil to form the roadbed.

Drainage systems – building culverts, stormwater channels and ditches to manage water flow.

Structures – constructing bridges, retaining walls and embankments.

Pavement works – laying the sub-base, base course and asphalt or concrete surface.

Ancillary works – installing road signage, guardrails, lighting and markings.

On the other hand, an ESMP is a detailed plan outlining how a road project will manage and mitigate potential environmental and social impacts during its design, construction and operational phases. It ensures that the project complies with national environmental laws and international standards, minimises negative effects on the environment (such as soil erosion, water pollution, noise and dust), also addressing social issues such as land acquisition, relocation, community safety and labour conditions.

*Full article available on Pressreader*

Share

Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Don't Miss

Customary marriages declared in community of property

MBABANE – The High Court has declared the long-standing practice of treating marriages under Eswatini Law and Custom as being out of community...

Inyatsi Construction building foundations of First World future

For more than four decades, Eswatini has witnessed one of the most significant periods of infrastructure development in its history. Under the leadership...

No more USA Visa processing in Eswatini

MBABANE – In a move that will significantly alter travel logistics for Eswatini nationals, the United States Embassy in Mbabane will cease accepting...

King moves to save Ncangosini residents from eviction

KONTSHINGILA – Hundreds of residents living on a privately owned farm at Ncangosini, Kontshingila, are set to be spared from eviction after an...

Each MP set for E1m handshake

MBABANE – When the 12th Parliament assumed office in 2023, an ordinary Member of Parliament (MP) was earning a basic monthly salary of...

Related Articles

I don’t have money to compensate them – Polycarp

MONENI – Moneni overseer Prince Polycarp says he does not have the...

New regulations to crack whip on online media

MBABANE - For sometime, government has struggled with creating a fair, ethical...

Chinese nationals seek hotel accommodation pending deportation

MBABANE – Eleven Chinese nationals have approached the High Court seeking an...

PM reaffirms Eswatini – Taiwan partnership upon arrival in Taiwan

MBABANE-Prime Minister (PM), Russell Mmiso Dlamini, has reaffirmed Eswatini’s enduring partnership with...