Before Bulembu gravel tarred, E45 million gone

Share
Government has already spent E28 033 000 on the Bulembu-Pigg’s Peak-Magoga Road project and is expected to withdraw a further E17 500 000 from the consolidated fund in the current financial year, which began on April 1, 2026, to complete compensations for affected properties.
Share

MBABANE – Government has already spent E28 033 000 on the Bulembu-Pigg’s Peak-Magoga Road project as of March 31, 2025.

It is also expected to withdraw a further E17 500 000 from the consolidated fund in the current financial year, which began on April 1, 2026, to complete compensations due to affected properties.

In total, government will have incurred a bill of E45 533 000 before the gravel road is even tarred. The total cost of the project, coded ‘T506/99’ and titled ‘Construction of Bulembu-Pigg’s Peak Road and Magoga (MR2 and MR20)’, is E948 million.

According to the Ministry of Public Works and Transport, the project has officially begun. The ministry explained that this commencement refers to the launch of an expression of interest tender for the updating of feasibility studies and detailed engineering designs. This means that previous designs, which were done at a cost, now require updating, and again at an additional cost.

The ministry stated that feasibility studies are being funded under Project T521, titled ‘Development of the Manzini Golf Course Interchange Project.’ It revealed that the procurement of a consultant for the update of feasibility studies and detailed designs has been completed, and that the contract was successfully negotiated with a responsive service provider.

The ministry reported that work on the updated feasibility studies and detailed designs started in December 2024 and was completed in June 2025.

Construction is expected to begin once the African Development Bank (AfDB), the potential financier, has approved the feasibility studies. Government further stated that negotiations are expected to start and conclude within the 2026 calendar year to allow construction to commence in 2027.

It must be noted that the Bulembu-Pigg’s Peak-Magoga Road is still unpaved yet continues to cost taxpayers millions. Deferred in previous financial years due to financial constraints, funds now appear to have been withdrawn to finance designs and compensation for affected properties.

To put the matter into perspective, the project has three tendering stages:

  • Road design and reviews.
  • Resettlements.
  • Compensation.

On July 26, 2020, the Times SUNDAY reported that E28 million had already been spent on the project, despite no visible progress on upgrading the road.

In its budget estimates for capital projects covering April 1, 2022, to March 31, 2025, the Ministry of Public Works and Transport projected that financial records could show an expenditure of E40 million in the 2023 financial year. However, it appears that the E40 million was either unutilised or not released to the ministry, despite being allocated by the Ministry of Finance.

*Full article available on Pressreader*  

Share

Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Don't Miss

Maloma Colliery calls for calm as wage talks continue

MBABANE - Maloma Colliery Ltd has offered employees a cumulative nine per cent salary increase over two years, but wage negotiations have reached...

DNA plan could swallow E126m of Home Affairs budget

MBABANE – Making DNA testing compulsory before issuing birth certificates could cost taxpayers about E126 million annually, enough to fund free Grade I...

Swazipharm blames ministry delays, commits to compliance

LOBAMBA – After being implicated in the delivery of medical drugs that were later recalled, prominent pharmaceutical supplier Swazipharm has reaffirmed its commitment...

Eswatini girls shine at Dance World Cup finals

MBABANE - Eswatini’s young ambassadors represented the nation with flawless charm at the ongoing Dance World finals in Ireland. Talent and Motion shared...

Shembe forgives Zulu King after video fallout

MBABANE – Members of the Nazareth Baptist Church in Eswatini have rallied behind His Holiness Unyazi Lwezulu Shembe after he publicly forgave Zulu...

Related Articles

Industrial Court declares Maloma Colliery strike unlawful

MBABANE – The Industrial Court has declared the strike by Maloma Colliery...

June EGCSE exams return

PIGG’S PEAK – The Examinations Council of Eswatini (ECESWA) has announced the...

Maloma Colliery calls for calm as wage talks continue

MBABANE - Maloma Colliery Ltd has offered employees a cumulative nine per...

DNA plan could swallow E126m of Home Affairs budget

MBABANE – Making DNA testing compulsory before issuing birth certificates could cost...