Understanding EEC’s service connection standards

Share
The Eswatini Electricity Company of (EEC) introduced a service connection standard pamphlet aimed at improving safety, consistency and quality in electrical installations across the country.
Share

The Eswatini Electricity Company of (EEC) introduced a service connection standard pamphlet aimed at improving safety, consistency and quality in electrical installations across the country.

The standard serves as a practical guide for homeowners, trade-tested electrical wiremen, EEC customers and operational staff involved in service connections and commissioning.

Purpose of the Service Connection Standard

This is designed to achieve three key objectives:

  • Provide clear guidelines for approved house and infrastructure wiring standards as set by EEC.
  • Create a common reference document for electrical wiremen, customer and EEC staff during service commissioning.
  • Promote uniformity and best practice in electrical installations nationwide.

The standard applies to both overhead and underground service connections and outlines approved minimum cable sizes, colour codes, breaker sizes and required electrical wiring materials.

Revised standard: Outdoor panel requirements

1. Service tensioning and mounting:

  • The service connection must be supported using approved fittings such as a tensioning bracket, pigtail or D-shackle.
  • A minimum 2.5-metre ground clearance is required for overhead connections, or an approved underground cable connection may be used.
  • The bracket must be mounted through the wall and securely screwed from inside the house.
  • Installation may also be done on a rafter (likabha).

2. Service conduit:

  • A 25mm PVC conduit is required to receive the aidec cable from the service pole.
  • The conduit must bend downward and enter the meter box from below.
  • A minimum 30cm spacing between the receiving conduit and the meter box is required to allow a smooth bend.

3. Meter box installation:

  • The meter box must be metallic, lockable and either installed into the wall or firmly mounted on it.
  • A minimum 1.5-metre ground clearance is required.
  • For non-concrete houses, both the meter box and distribution board (DB) must be installed into concrete.

 

4. Earthing requirements: Proper earthing is mandatory to ensure safety:

  • The earthing trench must be 50cm deep and extend at least 1 metre from the wall.
  • The earth spike must be driven 1 metre into the ground.
  • Earth resistivity must not exceed 10 Ohms.
  • Where resistivity is high, improvements may include:
  • Use of conductive cement
  • Crowfoot earthing
  • Importing and compacting suitable soil

A 16mm bare earth cable must be used, with all connections properly lugged. All non-electrical metallic components such as corrugated iron and plumbing must also be bonded to the earthing point.

 

5. Mains and communication conduits: 20mm conduits must be installed underneath the meter box and routed into the house.

Revised standard: Indoor panel requirements

1. Distribution board (DB):

  • The DB must be installed at a 1.6-metre ground clearance.
  • It should be easily accessible, such as in a passage or kitchen.

2. Minimum breaker sizes – The following breaker sizes are required:

  • 63A Earth leakage (mains)
  • 63A Stove
  • 40A Geyser
  • 30A Plug circuits
  • 20A Lighting circuits
  • 10A auxiliary circuits

3. Minimum wiring cable sizes

Approved minimum cable sizes include:

  • Earth (bare): 16mm
  • Mains: 10mm
  • Stove: 6mm
  • Geyser: 4mm
  • Plugs: 2.5mm
  • Lights: 1.5mm
  • Jumpers: 10mm

4. Plug and socket heights:

  • Plugs must be installed at least 30cm above the floor.
  • Stove isolators require a minimum 1-metre ground clearance.

 

5. Switch placement:

Switches must be installed at a 1.5-metre ground clearance.

They should not be positioned behind doors when opened.

Renovations and house extensions

Homeowners are advised to consult EEC before making changes:

Planned renovations: Consult EEC, pay a re-test fee and submit the required yellow form.

Extensions: A re-test is required when adding new circuits.

Unplanned faults: These must be reported to EEC for guidance.

 

Change of service type

For changes between overhead and underground service connections, customers must approach EEC for the relevant guidelines.

Share
Written by
Mthobisi Buthelezi

Mthobisi Buthelezi - Sections and Supplements Editor with the Times of Eswatini overseeing the publishing and content for the Motoring on Thursday, Property on Saturday, Tekulima (Farming) on Wednesday and Business Opportunities on Monday. Contact: 7936 3694 Email: mthobisib@times.co.sz

Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Don't Miss

Maloma Colliery calls for calm as wage talks continue

MBABANE - Maloma Colliery Ltd has offered employees a cumulative nine per cent salary increase over two years, but wage negotiations have reached...

Swazipharm blames ministry delays, commits to compliance

LOBAMBA – After being implicated in the delivery of medical drugs that were later recalled, prominent pharmaceutical supplier Swazipharm has reaffirmed its commitment...

DNA plan could swallow E126m of Home Affairs budget

MBABANE – Making DNA testing compulsory before issuing birth certificates could cost taxpayers about E126 million annually, enough to fund free Grade I...

Shembe forgives Zulu King after video fallout

MBABANE – Members of the Nazareth Baptist Church in Eswatini have rallied behind His Holiness Unyazi Lwezulu Shembe after he publicly forgave Zulu...

Eswatini girls shine at Dance World Cup finals

MBABANE - Eswatini’s young ambassadors represented the nation with flawless charm at the ongoing Dance World finals in Ireland. Talent and Motion shared...

Related Articles

Successful homes start long before construction

Building a home is one of the biggest investments most people will...

What happens to your property when you’re no longer here?

Imagine this… Your family already knows who should inherit your home. They...

Manzini Bus Rank relocates

Today marks a major shift for the city of Manzini as ongoing...

Valley View Centre: The pulse of business, lifestyle in Ezulwini

For decades, Ezulwini has occupied a special place in the hearts of...