Home Property How to acquire permit to build in Eswatini
Property

How to acquire permit to build in Eswatini

Share
Your agent should be familiar with the Building Act of 1968 and other regulations that will apply to your proposed building.
Share

When you want to construct or alter a building in Eswatini, you are required by the Building Act of 1968 to seek the approval of the appropriate Local Authority.

The exception is you do not seek approval for a dwelling occupied solely by the owner (household) for developments outside controlled areas.

You need to have a building permit for a dwelling being constructed in the urban areas and in controlled areas, all buildings used for public – purposes such as shops, butcheries, restaurants, warehouses, factories, churches, rental dwelling and flats, regardless of where they are built, must be approved through the Act.

The agent

Before seeking approval for the construction of a building, you must first have the building plans approved by an architect draughtsman.

This person will be your agent during the application process. Your agent should be familiar with the Building Act of 1968 and other regulations that will apply to your proposed building. If you have difficulty finding an agent, consult your local authority and they will refer you to a qualified agent.

The application

The agent will fill out the building application form (Form A). These forms can be obtained from the Local Authority Office or the Ministry of Housing and Urban Development in Mbabane.

Controlled areas

In the present Act controlled areas have been gazetted as follows:

1. An area falling within the urban boundaries of any city or town.

2.The area extending 366m on each side from the centre line of the Oshoek – Manzini Road.

3.An area or a building in rural areas intended to be used for public purposes e.g. shops, churches.

Submission of the application

When you submit your application to the appropriate local authority, you should submit a complete application that includes, among other things:

1. The application form;

2. Working drawings;

3. A site plan showing access to the public road, existing buildings, plot boundaries;

4. Allocation map;

5. All sewerage, drainage and water plans;

6. If required by the local authority in the case of structural frameworks, the attachment of a structural engineer to your project.

Four copies of all these documents are required. One set of drawings should use the conventional building/construction colour codes. In addition, there is an application fee that must be paid. This fee is paid on submission of the application.

Delays in the processing and approving of the application are sometimes caused by incomplete applications and by proposed building alterations that are not in compliance with the building regulations. Please refer to the Building Act of 1968, local building regulations, and consult your Local Authority on specific requirements of the building application.

Application review & approval process

As the diagram below indicates, the building application process has several stages. After the application is sent to the City or Townships Engineer’s Office.

The application is immediately forwarded to several government departments and public utilities for comments.

These recommendations are based on the function of the department or public utility. For example, the public health inspector looks at health related issues such as sanitary facilities and ventilation.

All the recommendations are compiled by the City or Townships Engineer. He or she might have comments on additional issues that need to be considered by the Local Authority.

The final decision on the application is made by the appropriate Local Authority. In the Cities of Mbabane and Manzini the building application is decided by the City Councils. All other areas in the Kingdom the decision is made by the Local Authority after a recommendation by the Principal Secretary Ministry of Housing and Urban Development.

Appeals

Any person who is aggrieved by the decision issued by the engineer may appeal to the Building Appeals Tribunal within 14 days after receipt of the notice or decision. Please consult your local authority.

Issued by Urban Government Department, Ministry of Housing and Urban Development, Government of Kingdom of Eswatini.

Share
Written by
Mthobisi Buthelezi

Mthobisi Buthelezi - Sections and Supplements Editor with the Times of Eswatini overseeing the publishing and content for the Motoring on Thursday, Property on Saturday, Tekulima (Farming) on Wednesday and Business Opportunities on Monday. Contact: 7936 3694 Email: mthobisib@times.co.sz

Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Don't Miss

‘Cat’ Matlala ID saga: Home Affairs official dismissed

MBABANE – Nonhlanhla Malambe, the Home Affairs official found guilty over the issuance of Eswatini national documents to Vusimuzi ‘Cat’ Matlala, has been...

 MaMkhize absent as Eswatini team suffer 2nd  defeat

NHLANGANO – Mbabane Highlanders AM suffered another painful defeat without President Shauwn ‘MaMkhize’ Mkhize in the stands, as Nsingizini Hotspurs edged them 1-0...

Ex-magistrate, another allegedly disobey court orders

MBABANE – Jail time has been sought for former Magistrate Dumisani Magagula and an individual with whom he is alleged to have disobeyed...

10-litre container of drugs allegedly found with clinic guard

VUVULANE – Community members reportedly recovered a 10-litre container of medication from a security guard at Vuvulane Rural Clinic, raising concerns of theft....

Indlovukazi arrives in UAE for official visit

Her Majesty Indlovukazi has arrived safely in the United Arab Emirates (UAE) where she is on an official visit. Her Majesty arrived around...

Related Articles

Clear overgrowth before summer dangers take hold

Summer brings warmer temperatures, rainfall and rapid vegetation growth, transforming once-clear plots...

Solar training to offer youth new opportunities

As electricity costs continue to put pressure on household budgets and businesses,...

Who can afford to begin? The first home in Eswatini

By Musa Nhleko A young couple works in Matsapha, rents in Manzini...

Don’t relive last summer’s fears!

Storms can arrive with little warning, bringing strong winds, heavy rain and...