Home Business EEC’s Maguga Station expansion unlocks engineering, financing opportunities
Business

EEC’s Maguga Station expansion unlocks engineering, financing opportunities

Share
Construction of the additional 10MW hydropower unit at the existing Maguga Power Station site has been impeded by financial challenges the utility has been experiencing in the recent past. (File pic)
Share

MBABANE – EEC has opened a significant investment and engineering opportunity through a tender for the development of an additional 10-megawatt (MW) hydropower generating unit at the Maguga Hydropower Station.

The utility is seeking suitably qualified engineering, procurement and construction (EPC) contractors, developers, investors or consortiums capable of not only constructing the new power unit, but also arranging or providing the financing required to bring the project to fruition.

The opportunity comes as the Eswatini Electricity Company (EEC) seeks to close a financing gap that has delayed the planned expansion of the Maguga facility.  Construction of the additional 10MW hydropower unit at the existing Maguga Power Station site has been impeded by financial challenges the utility has been experiencing in the recent past.

To close the financing gap, the utility wishes to appoint a suitably qualified EPC contractor, developer, investor, or EPC/developer/investor-led consortium that can provide or arrange the required project financing and enter into commercial agreements that will be beneficial to both parties. According to the Request for Proposals (RFP), the existing Maguga station has two 10MW generating units, while the proposed expansion would add a third 10MW unit alongside the existing plant. The project is therefore being positioned as more than a conventional construction tender, with EEC inviting private-sector capital, international engineering expertise and structured finance to participate in the expansion of the country’s renewable energy infrastructure. The RFP provides investors with several possible routes to participate in the project. These include an EPC-plus-finance arrangement, where the successful contractor would deliver the project on a turnkey basis while arranging financing through mechanisms such as export credit, commercial debt or development finance.

Another option is a Build-Own-Operate-Transfer (BOOT) or Independent Power Producer (IPP) model. Under this arrangement, a developer would finance, construct, own, operate and maintain the facility for an agreed period under a long-term Power Purchase Agreement before transferring the asset to EEC or another designated entity. EEC has also made provision for an operation and maintenance tariff model, under which the utility would retain ownership while a developer operates and maintains the plant for an agreed tariff.

The RFP indicates that the final commercial structure could ultimately be a combination of these models, depending on negotiations with shortlisted bidders, financing arrangements and regulatory approvals. An indicative concession period of between 20 and 30 years from the commercial operations date has been proposed where a concession or BOOT structure is adopted, with the term intended to support project bankability.

This creates an opportunity not only for construction companies but also for infrastructure investors, project developers, financial institutions, export credit agencies and development finance institutions to participate in the project.

The engineering scope is extensive.

The successful bidder will be expected to undertake detailed engineering and design for the new generating unit and associated facilities, procure and manufacture equipment, transport and instal components, execute civil and hydraulic works, undertake steel works and install electro-mechanical and electrical systems. The scope further covers control and protection systems, transmission or substation modifications, testing, commissioning, performance testing, reliability runs and eventual handover.

The project is classified as a brownfield expansion, meaning the new facility must be integrated into an existing operational hydropower station.

This creates opportunities for specialist engineering companies with experience in hydropower extensions, electro-mechanical installations, grid integration, automation, civil works, SCADA systems, cyber and physical security, environmental management and project commissioning. The successful bidder will also be responsible for training EEC personnel and providing operation and maintenance manuals, spare parts and special tools.

Share
Written by
Nhlanganiso Mkhonta

Nhlanganiso Mkhonta serves as Business Editor at the Times of Eswatini. He reports on business, economics, finance, investment, entrepreneurship and public policy, producing insightful coverage and analysis of the issues driving Eswatini’s economy and the wider African business environment.

Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Don't Miss

Chief Justice Bheki Maphalala passes on

MBABANE- Chief Justice Bheki Maphalala has died, according to reports emerging on Thursday. Maphalala is reported to have passed away while receiving treatment...

Schools open as scheduled – PS

MBABANE –Principal Secretary in the Ministry of Education and Training, Nanikie Mnisi, has affirmed that schools will reopen as scheduled in accordance with...

Mbuso Simelane accused of attempts to divert E10m public funds

MBABANE – The Eswatini Medical Christian University (EMCU) Council has alleged that the Chairman of the committee appointed to investigate the affairs of...

Gogo and S’lwane launch website

MBABANE — After at least half a decade in the game, Eswatini’s most enterprising stand-up comedy and content creation duo, Gogo Eswatini and...

Man loses over E100 000

... facata strikes again MANZINI – A 58-year-old man of Ngwane Park has lost E118 172.91 to unknown callers in what police have...

Related Articles

New COMESA rules reshape regional competition landscape

MBABANE - The new COMESA Competition and Consumer Protection Regulations, 2025, introduce...

Revenue Tribunal targets efficiency as appeals rise

MBABANE – The Revenue Appeals Tribunal Eswatini (RATE) has pledged to strengthen...

Retail, wholesale sector steps up for e-invoicing pilot

MBABANE – Eswatini’s retail and wholesale businesses have stepped forward to support...

SBS Bank holds 1st AGM, nominates new Board

MBABANE - SBS Bank Eswatini has taken another major step towards becoming...