Home Business EEC’s Maguga Station expansion unlocks engineering, financing opportunities
Business

EEC’s Maguga Station expansion unlocks engineering, financing opportunities

Share
Construction of the additional 10MW hydropower unit at the existing Maguga Power Station site has been impeded by financial challenges the utility has been experiencing in the recent past. (File pic)
Share

MBABANE – EEC has opened a significant investment and engineering opportunity through a tender for the development of an additional 10-megawatt (MW) hydropower generating unit at the Maguga Hydropower Station.

The utility is seeking suitably qualified engineering, procurement and construction (EPC) contractors, developers, investors or consortiums capable of not only constructing the new power unit, but also arranging or providing the financing required to bring the project to fruition.

The opportunity comes as the Eswatini Electricity Company (EEC) seeks to close a financing gap that has delayed the planned expansion of the Maguga facility.  Construction of the additional 10MW hydropower unit at the existing Maguga Power Station site has been impeded by financial challenges the utility has been experiencing in the recent past.

To close the financing gap, the utility wishes to appoint a suitably qualified EPC contractor, developer, investor, or EPC/developer/investor-led consortium that can provide or arrange the required project financing and enter into commercial agreements that will be beneficial to both parties. According to the Request for Proposals (RFP), the existing Maguga station has two 10MW generating units, while the proposed expansion would add a third 10MW unit alongside the existing plant. The project is therefore being positioned as more than a conventional construction tender, with EEC inviting private-sector capital, international engineering expertise and structured finance to participate in the expansion of the country’s renewable energy infrastructure. The RFP provides investors with several possible routes to participate in the project. These include an EPC-plus-finance arrangement, where the successful contractor would deliver the project on a turnkey basis while arranging financing through mechanisms such as export credit, commercial debt or development finance.

Another option is a Build-Own-Operate-Transfer (BOOT) or Independent Power Producer (IPP) model. Under this arrangement, a developer would finance, construct, own, operate and maintain the facility for an agreed period under a long-term Power Purchase Agreement before transferring the asset to EEC or another designated entity. EEC has also made provision for an operation and maintenance tariff model, under which the utility would retain ownership while a developer operates and maintains the plant for an agreed tariff.

The RFP indicates that the final commercial structure could ultimately be a combination of these models, depending on negotiations with shortlisted bidders, financing arrangements and regulatory approvals. An indicative concession period of between 20 and 30 years from the commercial operations date has been proposed where a concession or BOOT structure is adopted, with the term intended to support project bankability.

This creates an opportunity not only for construction companies but also for infrastructure investors, project developers, financial institutions, export credit agencies and development finance institutions to participate in the project.

The engineering scope is extensive.

The successful bidder will be expected to undertake detailed engineering and design for the new generating unit and associated facilities, procure and manufacture equipment, transport and instal components, execute civil and hydraulic works, undertake steel works and install electro-mechanical and electrical systems. The scope further covers control and protection systems, transmission or substation modifications, testing, commissioning, performance testing, reliability runs and eventual handover.

The project is classified as a brownfield expansion, meaning the new facility must be integrated into an existing operational hydropower station.

This creates opportunities for specialist engineering companies with experience in hydropower extensions, electro-mechanical installations, grid integration, automation, civil works, SCADA systems, cyber and physical security, environmental management and project commissioning. The successful bidder will also be responsible for training EEC personnel and providing operation and maintenance manuals, spare parts and special tools.

Share
Written by
Nhlanganiso Mkhonta

Nhlanganiso Mkhonta serves as Business Editor at the Times of Eswatini. He reports on business, economics, finance, investment, entrepreneurship and public policy, producing insightful coverage and analysis of the issues driving Eswatini’s economy and the wider African business environment.

Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Don't Miss

King shaped Princess Lindiwe into epitome of excellence

SIDVOKODVO – Prince Guduza has credited His Majesty King Mswati III with shaping Princess Lindiwe into the woman mourners celebrated at her funeral...

FNB probe uncovers E20m fraud syndicate

BY MBONGISENI NDZIMANDZE AND KWANELE DLAMINI MBABANE – Investigations into the alleged fraud committed at FNB Eswatini have uncovered a syndicate involving businessmen,...

Home Affairs official fired in insurance scam as…

... man declared dead while alive MBABANE – A living man was declared dead after a Home Affairs official issued a death certificate...

Butsegetsege set to light up Eswatini for Kagogo Weekend

MBABANE — Excitement has reached a fever pitch across the kingdom as viral cultural sensation Mavusane Cyzweh, widely known as Butsegetsege, officially confirms...

Royal Swazi Reopening in sight

MBABANE- What has seemed like an eternity, the Royal Swazi Hotel could finally be opening its doors before the end of the year....

Related Articles

Eswatini economy expands 6.5% in Q2

MBABANE – Eswatini’s real gross domestic product (GDP) grew by 6.5 per...

EWADE pauses new farmer intake into Hamba Ubuye

MBABANE - In this current farming season (2026/27), the Eswatini Water and...

MTN’s new solution to shield businesses from internet disruptions

EZULWINI – MTN Eswatini has launched a new connectivity solution called MTN...

MTN urges businesses to turn AI into practical value

EZULWINI - Businesses should focus on how artificial intelligence can create practical...