Somhlolo roadmap missing

Share
An aerial view of Somhlolo National Stadium. (Pic: Nsingizini Facebook)
Share

MBABANE – Revealed!

The upgrading of Somhlolo National Stadium has faced a 16-year administrative delay, with the Ministry of Sports, Culture and Youth Affairs unable to produce the original blueprint or roadmap for the project.

The auditor general (AG) has revealed that the ministry failed to produce a Project Initiation Document for Project R22499.

This crucial document is required to serve as the implementation roadmap, outlining cost estimations and establishing a baseline for monitoring, evaluation and performance tracking.

According to the Public Accounts Committee (PAC) report, the multi-million Emalangeni project commenced in 2010, but remains uncompleted 16 years later. The report noted that the lack of a baseline document has heightened risks of poor coordination, unclear accountability; budget overruns and compromised structural quality.

The controlling officer submitted to the committee that the records cannot be located. The ministry reportedly attempted to retrieve a duplicate copy from the Ministry of Economic Planning and Development, but came up empty-handed. Only progress reports from 2014 and 2015 were recovered.

The controlling officer stated that while he believes the document exists, it simply cannot be found.

Despite the absence of the foundational paperwork to track historical expenditure, the minister for Sports, Culture and Youth Affairs requested approximately E42 million in March 2026 for further works, which the report noted lacked a clear breakdown of how the funds would be used.

It is worth noting that this E42 million budget estimate, originally intended for the ongoing rehabilitation of the stadium, is now expected to be redirected to Microprojects.

*Full article available on Pressreader*  

Share

Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Don't Miss

New bus fares to take effect next week

MANZINI – Commuters will start paying higher bus fares next week after transport operators begin displaying notices announcing the revised tariffs. The new...

Illegal foreign-owned businesses given 1 year to close

LOBAMBA – Foreign-owned businesses found operating in violation of the country’s laws and regulations have been given 12 months to regularise their operations...

Another cup final for MaMkhize’s Eswatini team

(At Somhlolo National Stadium) Highlanders AM.....(0)0 Ubombo Sugar........(0)0  Highlanders won 5-3 on penalties) MBABANE - Mbabane Highlanders AM reached the PLE Charity Cup...

FNB offers more incentives to attract new customers

MBABANE - FNB Eswatini has introduced a campaign offering qualifying customers repayment holidays, cash-back incentives and additional family protection benefits. This comes as...

King extends army Commander Fakudze’s service

MBABANE – His Majesty King Mswati III has extended the service of Umbutfo Eswatini Defence Force (UEDF) Commander General Moses Mashikilisane Fakudze, allowing...

Related Articles

Eswatini, Seychelles strengthen Olympic ties

MBABANE – Eswatini and Seychelles are strengthening Olympic ties through a professional...

Eswatini target second netball win against SA Defence

MBABANE – Fresh from demolishing SAPS 97-14, Eswatini’s men’s national netball team...

Eswatini U-23 victory over Algeria wins hearts

MBABANE – The impressive run of the national Under-23 side in the...

South America rivals for Sihlangu!

MBABANE – With their European adventure gathering momentum, Sihlangu are set for...